Feb 25, 2026

BNF Engineers Ltd. Completed DESCO Cable Trench Project

 

Cable Trench


Project scope summary

Work covered: mobilization/demobilization; site clearing; dismantling of RCC elements; earth excavation and disposal; sand filling; mass concrete and RCC works; polythene sheet supply/laying; reinforcement.

ent supply; steel built-up sections; bolts; HDPE pipes.

Measurement and payment: quantities to be measured and accepted by the Engineer‑in‑charge; payments proportionate to overall contract progress.


Itemized Bill of Quantities (BOQ) — structured for tendering and measurement

tem No.

Description

Unit

Measurement basis

Remarks

1

Mobilization, site cleaning, dressing, stockpiling, and demobilization

Lump sum

As per the site area determined by the Engineer‑in‑charge

Include safety, security, and temporary facilities

2

Dismantling R.C.C. beam, lintel, column, drop wall, sun shade; brooming, cleaning, and debris disposal

Volume of dismantled concrete accepted by the Engineer‑in‑charge

Include cutting, lowering from any height, and temporary supports

3

Earthwork — excavation in foundation trenches up to 1.5 m depth (max lead 10 km)

Net excavated volume in trenches

Include shoring if required; exclude rock unless specified

4

Transport and disposal of excavated earth withina  30 km radius (loading/unloading)

m³ or per truck

Volume or truckloads accepted by the Engineer‑in‑charge

Include leveling and dressing at the disposal site

5

Sand filling in foundation trenches and plinth in 150 mm layers (F.M. ≥ 0.5)

Compact volume in place to finished level

Compaction to 95% dry density (Modified Proctor); include watering/ramming

6

Mass concrete in foundation (1:2:4) with brick chips and local sand

Gross concrete volume placed

Include mixing, placing, and curing; exclude reinforcement & shuttering

7

Supply & laying single layer polythene sheet (1 kg per 6.5 m²) below the concrete/floor

Area covered

Include laps, sealing, and fixing

8

RCC works (1:1.5:3) measured on gross concrete section (f'c = 25 MPa)

Gross concrete volume of structural elements up to the plinth

Rate excludes reinforcement, fabrication, shuttering & lab test fees

9

Reinforcement Grade 400 (B400DWR/B420DWR) — supply (up to ground floor)

tonne or kg

Weight of bars placed and accepted

Include cutting, bending, and tying if specified separately

10

Shuttering (Steel) — supply, fabrication, installation

Area of formwork in contact with concrete

Include removal after specified curing time; exclude centering if separate

11

Built‑up steel sections (columns, beams, rafters, bracings, struts) up to level‑4 (ASTM A36)

tonne or kg

Weight of fabricated & erected steel

Include testing of plates, primer application

12

Solid SS royal bolt with cap

each

Number of bolts supplied & fixed

Specify size, grade and fixing method

13

HDPE pipe 110 mm OD, wall thickness 4.2–4.8 mm

m

Length laid and accepted

Include fittings, jointing, testing if required

14

HDPE pipe 160 mm OD, wall thickness 6.2–7.0 mm

m

Length laid and accepted

Include fittings, jointing, testing if required


Measurement and payment notes

  • Acceptance authority: All measurements, tests, and approvals to be certified by the Engineer‑in‑charge.
  • Payment basis: Items paid on measured quantities or lump sum as specified; mobilization/cleaning payments to be proportionate to overall contract progress and based on ground area as determined by the Engineer‑in‑charge.
  • Excluded items: Unless explicitly stated, rates exclude reinforcement fabrication/placing, shuttering (where noted), laboratory test fees, and specialized temporary works. These must be priced separately or clarified in the tender.


Quality, testing and standards

  • Concrete: Nominal mixes and specified compressive strengths to comply with ACI / BNBC; cement BDS EN‑197‑1‑CEM‑I, 52.5N.
  • Aggregates & sand: Sand F.M. and grading as specified; stone chips to ASTM C‑33.
  • Rebar: Grade 400 complying with BDS ISO 6935‑2:2016 / ASTM A615; supply certificates and mill test reports.
  • Steel plates: ASTM A36; provide test certificates and apply primer as specified.
  • Testing: Contractor to carry out standard tests (slump, compressive strength, proctor, aggregate gradings) and submit reports; laboratory fees excluded unless stated.


Safety, environment, and disposal

  • Site safety: Contractor to maintain a safe working environment, provide PPE, barricading, signage, and traffic management.
  • Debris & spoil: Stockpile and dispose at Engineer‑approved location within 30 km; include loading/unloading, leveling at disposal site.
  • Environmental controls: Dust suppression, silt control, and proper handling of waste materials to comply with local regulations.