Jun 24, 2026

Difference Between RCC and PCC

Tie Beam

PCC is plain concrete used as a non‑structural bedding/blinding layer (strong in compression only); RCC is concrete with steel reinforcement used for all load‑bearing members (resists tension, bending, shear) — in projects, use PCC for leveling/blinding and RCC for beams, slabs, columns, and footings.

Definitions and core engineering differences

  • Rigid Pavement Design

  • Plain Cement Concrete (PCC): cement + sand + coarse aggregate + water; no steel reinforcement. Used where only compressive strength is required.

  • Reinforced Cement Concrete (RCC): same concrete matrix plus steel reinforcement (rebars/mesh) so the composite resists tension, bending, and shear; used for structural elements.

  • RCC Beam

Design considerations (engineering view)RCC beam details

  • Load paths: Concrete carries compressive forces; steel carries tensile forces and controls crack widths. Design must follow relevant codes (e.g., BS/EN, ACI, or local BNBC/BD codes, depending on project).

  • Material properties: Typical PCC mixes on site: 1:2:4 or 1:3:6 (cement : sand: aggregate) for non‑structural work; RCC uses a designed mix (e.g., M20, M25) with specified slump, cover, and rebar grade.

  • Concrete mix ratio - PSI Strength - M5 to M70 grades 28 days

Construction practices

  • PCC placement: Used as blinding under footings, leveling bed, sub‑base for slabs and pavements; compact, finish, and cure for a minimum of 7 days to reduce shrinkage cracks.

  • RCC placement: Requires formwork, accurate rebar placement with specified cover, staged concreting, vibration, and curing; quality control (cube tests, slump tests) is essential. Poor cover or inadequate compaction leads to corrosion and loss of capacity.

Colour Mixing Ratio Chart

Uses and typical examples

  • PCC: blinding under footings, base for floor finishes, temporary access roads, pipe bedding.

  • RCC: beams, slabs, columns, footings, retaining walls, water tanks, bridges, seismic‑resistant frames.

Quick comparison table

CriterionPCCRCC
CompositionCement; sand; aggregate; waterSame + steel reinforcement
Primary strengthCompression onlyCompression + tension (via steel)
Typical usesBlinding; sub‑base; non‑structuralStructural members: beams, slabs, columns
Cost & laborLowerHigher (steel, formwork, skilled labor)
Durability under bending/quakePoorGood if designed per code

Decision guide and practical tips for projects

  1. If the element carries bending/tension or supports live loads → RCC.

  2. If only leveling/blinding/sub‑base → PCC.

  3. Specify concrete grade, rebar grade, minimum cover, and curing regime in drawings.

Risks, maintenance, and lifecycle

  • Risk: Inadequate cover or poor compaction in RCC → corrosion of steel and structural failure.

  • Maintenance: Inspect for cracks, ensure drainage to avoid saturation; repair spalls and maintain protective covers.


Recommended Mix Designs (M‑grades)

Short answer — engineering, design, and local cost: Use PCC (plain concrete) for non‑structural blinding and bedding; use RCC (reinforced concrete) for all load‑bearing members because steel carries tension while concrete carries compression. Recommended design mixes: M20 (typical RCC), M25 (common design mix), and M30 (higher strength) with the material quantities below; typical rebar choices for slabs/beams/columns are listed, and Ready‑Mix Concrete (RMC) in Dhaka currently costs about ৳11,300–৳14,100 per m³ (based on RMC rates per CFT).

1) Recommended mix designs (per 1 m³, engineering values)

GradeCement (kg/m³)Water (kg/m³)Fine agg (kg/m³)Coarse agg (kg/m³)
M20 (nominal)383~192~575~1150.
M25 (design mix)426191.6662.81101.8.
M30 (design mix)450180~600~1150.
  • Guide for the right mixture of concrete
  • Concrete ingredients
  • :: Self Consolidating High Performance Concrete
  • Typical Concrete Mix: Mixing Ratios

Notes: M20 is often used for general residential RCC; M25/M30 should be design‑mixed per IS/ACI using local aggregate tests and target mean strength. Always run trial mixes and control w/c ratio for durability.

2) Typical rebar schedules (practical engineering guidance)

MemberTypical main barsStirrups/tiesApprox. steel (kg/m³ concrete)
One‑way slab8–10 mm @ spacing6–8 mm distribution80–100 kg/m³ (typical).
Two‑way slab / flat slab10–12 mm8 mm100–150 kg/m³.
Beams (residential)12–16 mm main; 16 mm for larger spans8–10 mm stirrups150–250 kg/m³ (varies with span).
Columns16–25 mm (4–8 bars)8–10 mm ties @ 100–200 mm200–300+ kg/m³ (depends on load).
Footings10–20 mm depending on size8–10 mm75–200 kg/m³ (varies).

Important: These are typical site practice ranges for preliminary estimating; final bar sizes/spacing must come from structural design drawings and code checks.

3) Localized cost guidance for Dhaka (practical estimate)

  • RMC price in Dhaka: ৳320–৳400 per CFT≈৳11,300–৳14,100 per m³ (1 m³ = 35.3147 CFT).

  • Material retail prices (examples): Cement 50 kg bag ≈ ৳520–৳600; sand ≈ ৳45–৳65 per CFT; stone chips ≈ ৳90–৳130 per CFT. Use these to estimate site‑mixed concrete cost if not using RMC.

Rule of thumb: For small jobs, RMC is often cost‑competitive once labour, formwork, and curing are included; for remote or tiny pours, site‑mixing with local materials may be cheaper but requires strict quality control.

4) Design & construction tips (risks and mitigation)

  • Control w/c ratio and curing to meet target strength and durability; specify minimum cover for rebar to avoid corrosion in Dhaka’s humid climate.

  • Use design mix for M25+ (lab‑tested) rather than nominal mixes for critical members.

  • Quality checks: slump tests, 7/28‑day cube tests, and inspection of rebar placement and cover.

Concrete Mixing Ratio Chart

No comments:

Post a Comment